right now it is an excel spread sheet, we are developing a system to interface that and some others that would likely be linked to this later on
it would be Presley's Production Planner. That's what the whole shop operates off of right now. We just need to see what that looks like otherwise the shop has to filter down to what they need to…
Keep the change order (as built), so the shop confirms the new pages.
we will need to talk about this more, it needs to be really be based off the shop schedule. that would determine priority and order. it will need to link live to the scheduler so if jobs get…
the data book and each packets documents with a manifest. It would need to go at filing
lets just do the customer copy for now. do not worry about including the full history in the databook
no just A new drawing rev, a quantity change or a removed operation opens a change order.
the supervisor needs to approve every short separately, and the packet can not be fully completed until all shorts are accounted for and the job is truly completed
no. the department checklists are created by the supervisor and do not reference over to Q.C.
lets go with just project management for now
I would say keep as built for now. Just flag on ticket hours