Partspecs, title or folded-operation target changes on an in-shop packet #11

Closed
opened 2026-10-19 02:50:14 +00:00 by spencerm · 4 comments
Owner

Built as the default: no change order for these, as the old build; the new values are stored and shown.

To answer: keep, or open a change order for some of them.


Plan reference: Q12 in docs/PLAN.md (open questions). Answer here; the build takes the default until then.

**Built as the default:** no change order for these, as the old build; the new values are stored and shown. **To answer:** keep, or open a change order for some of them. --- Plan reference: Q12 in [docs/PLAN.md](https://gt.pescoinc.biz/spencerm/PacketStation/src/branch/main/docs/PLAN.md) (open questions). Answer here; the build takes the default until then.
spencerm added the phase 3decision: Seth labels 2026-10-19 02:50:14 +00:00
Collaborator

Please provide more information

Please provide more information
Author
Owner

More detail, since you asked.

When VISUAL changes a packet that is already in the shop, Packet Station handles two kinds of change differently:

  • A new drawing rev, a quantity change or a removed operation opens a change order. The shop has to verify it before work goes on.
  • Three smaller fields are just updated, with no change order: the partspecs (the planner instructions text on the operation), the packet title, and the target hours of folded operations (operations listed on the packet but not run as their own packet). The new values are stored, shown on the packet and logged. That is what the old build did.

The question: should any of those three open a change order instead, so the shop has to confirm it? Reply "keep", or name the ones that should.

More detail, since you asked. When VISUAL changes a packet that is already in the shop, Packet Station handles two kinds of change differently: - A new drawing rev, a quantity change or a removed operation opens a change order. The shop has to verify it before work goes on. - Three smaller fields are just updated, with no change order: the partspecs (the planner instructions text on the operation), the packet title, and the target hours of folded operations (operations listed on the packet but not run as their own packet). The new values are stored, shown on the packet and logged. That is what the old build did. The question: should any of those three open a change order instead, so the shop has to confirm it? Reply "keep", or name the ones that should.
Collaborator

no just A new drawing rev, a quantity change or a removed operation opens a change order.

no just A new drawing rev, a quantity change or a removed operation opens a change order.
Author
Owner

Noted: only a new drawing rev, a quantity change or a removed operation opens a change order. Partspecs, title and folded-operation targets stay plain updates, as built. Recorded in docs/PLAN.md (PR 53). Closing.

Noted: only a new drawing rev, a quantity change or a removed operation opens a change order. Partspecs, title and folded-operation targets stay plain updates, as built. Recorded in docs/PLAN.md (PR 53). Closing.
Sign in to join this conversation.
2 Participants
Notifications
Due Date
No due date set.
Dependencies

No dependencies set.

Reference: spencerm/PacketStation#11