Warehouse release gate enforced on the server #16

Closed
opened 2026-10-19 02:50:16 +00:00 by spencerm · 2 comments
Owner

Two rules: every line not N/A is pulled or on an open short, and every pulled line that issued pieces has a heat unless N/A or a sub-assembly. The old build checked both on the screen only.

Built as the default: both on the server, so a release cannot bypass them.

To answer: keep or relax.


Plan reference: Q19 in docs/PLAN.md (open questions). Answer here; the build takes the default until then.

Two rules: every line not N/A is pulled or on an open short, and every pulled line that issued pieces has a heat unless N/A or a sub-assembly. The old build checked both on the screen only. **Built as the default:** both on the server, so a release cannot bypass them. **To answer:** keep or relax. --- Plan reference: Q19 in [docs/PLAN.md](https://gt.pescoinc.biz/spencerm/PacketStation/src/branch/main/docs/PLAN.md) (open questions). Answer here; the build takes the default until then.
spencerm added the phase 4decision: Seth labels 2026-10-19 02:50:16 +00:00
SethD was assigned by spencerm 2026-10-19 02:50:53 +00:00
Collaborator

this we must keep. If we relax, they will start sending parts through without filling the heat map. Warehouse is to fill the heat map on the parts they send.

this we must keep. If we relax, they will start sending parts through without filling the heat map. Warehouse is to fill the heat map on the parts they send.
Author
Owner

Kept as built and recorded in docs/PLAN.md (PR 51). Nothing changes in the build. Closing.

Kept as built and recorded in docs/PLAN.md (PR 51). Nothing changes in the build. Closing.