Build Seth's changes C1 to C11 (Gitea issues 1, 8, 18, 23, 24, 25, 27, 31, 32, 33, 36)
- C1 (issue 1): over target follows VISUAL ticket hours, not the timer. - C2 (issue 24): a Q.C. reject always needs a reason; accept needs an NCR number after a reject without one. - C3 (issue 25): an incomplete unit ITP blocks filing. - C4 (issue 27): prints open the print dialog on the page, no new tab. - C5 (issue 31): filing is blocked while VISUAL shows a work order open; the feed sets vclosed on VISUAL packets. - C6 (issue 8): the data book leaves out the history pages. - C7 (issue 18): the supervisor approves each received short; accept and filing wait for it. - C8 (issue 23): per-department checklists, edited by the department supervisor or Admin, frozen at START. - C9 (issue 32): Q.C. and Clerical may run the stamp check. - C10 (issue 33): the PM screen and reports are for PS-ProjectMgmt and Admin only. - C11 (issue 36): the Stall screen lists the packets assigned to the welder, at the supervisor's stall. Migration 0011. Docs: PLAN (also issue 9 confirmed, issue 4 asked), POLICY, SECURITY, SCHEMA, FEED, README, CHANGELOG. Co-Authored-By: Claude Opus 5.5 <[email protected]>
This commit is contained in:
@@ -55,6 +55,10 @@ class PacketState:
|
||||
filler_set: bool = False
|
||||
qc_missing: tuple[str, ...] = () # the old qcMissing() list, computed by the read model
|
||||
has_qc_sent: bool = False # qc_inspections row exists for the current stage
|
||||
shorts_unapproved: int = 0 # open shorts plus received shorts the supervisor has not approved (C7)
|
||||
itp_open: bool = False # the packet's unit has an ITP that is not complete (C3)
|
||||
ncr_required: bool = False # a Q.C. reject since the last accept has no NCR number (C2)
|
||||
visual_open_wos: tuple[str, ...] = () # the work orders the feed last saw open in VISUAL (C5)
|
||||
|
||||
|
||||
SYSTEM_FEED = Principal(user_id=None, system="visual-feed")
|
||||
|
||||